Unread 01-01-2017, 09:16 PM   #1
Ksue28
Registered User
 
Join Date: Jan 2017
Posts: 7
Is this an acceptable tile job?

Hi all. I'm new here.

We had water damage in our home and part of the redo is our main bathroom. Because we had arabesque/lantern tile in there originally, we decided to go with it again tho in a different color. Am I nitpicking this job to death? Is this an acceptable professional install? I don't want to call my tiler back out again if this is all within the realm of normal and expected.

First of all, the original job around the vent was awful. We asked him to come redo only to find out he cracked a tile in the process and used caulk instead of grout, so that when I went to pull up the vent cover to replace, the caulk came with it. Now it looks just as bad as it did before. See pics.

The second thing is the finish work, like around my door frame. Why is this so ugly looking? Why not use a full tile? See pic.

We have some tiles far apart and some super close. (These came on a 12x12 sheet).

And finally, there are four different places where the thinset was taller than the tile so those areas took no grout. I was told when the grout dries to just chip out the thinset and fill in the gap with caulk. Why is this my job? And is caulk even going to last, considering that the caulk around the vent is still wet and rubbery five days later?

I'm also bothered by the fact that he didn't pull out the scratched tiles and replace with good ones. Seems that would be obvious, so I have 3-4 tiles in a cluster all scratched through that look unsightly.

This, along with a tub surround w basic 4x4 white tiles, cost 2300 in labor. Reasonable?

Thanks a ton for any insight.
__________________
KSue
Ksue28 is offline   Reply With Quote
Sponsored Links
Unread 01-01-2017, 09:19 PM   #2
Ksue28
Registered User
 
Join Date: Jan 2017
Posts: 7
Pics below

1. Gaps around vent where there is no grout
2. You can't tell but the glob on the left is rubbery caulk and is going down into the vent. It doesn't dry. It's like gum.
3. Lots of grout on and around both door frames.
4. Tiles right up against one another.
5. Thinset appears as white dots. Baseboard won't cover this and there are about 4 more spots like this on the floor where he told me to chip it out and replace w caulk. ?
Attached Images
     
__________________
KSue
Ksue28 is offline   Reply With Quote
Unread 01-01-2017, 09:28 PM   #3
Ksue28
Registered User
 
Join Date: Jan 2017
Posts: 7
This is why I called him back out the second time. I was very unhappy with this.
Attached Images
  
__________________
KSue
Ksue28 is offline   Reply With Quote
Unread 01-01-2017, 10:32 PM   #4
PetrH
Registered User
 
Join Date: Feb 2012
Location: Chilliwack, B.C.
Posts: 1,405
You don't need us to tell you that this isn't good enough. When I see workmanship like this, my first question tends to be: how was the shower waterproofed?

This was clearly done by someone who does not know how to set tile.

You paid for a professional job and you didn't get one. You should refuse payment it there is any money outstanding.
__________________
Petr
PetrH is offline   Reply With Quote
Unread 01-01-2017, 10:37 PM   #5
Ksue28
Registered User
 
Join Date: Jan 2017
Posts: 7
What kind of waterproofing is needed? All I know is that cement board was put up and thinset over that. Then tile.
__________________
KSue
Ksue28 is offline   Reply With Quote
Unread 01-01-2017, 10:40 PM   #6
Tool Guy - Kg
Moderator -- Wisconsin Kitchen & Bath Remodeler
 
Tool Guy - Kg's Avatar
 
Join Date: Feb 2005
Location: Oak Creek, WI
Posts: 21,648
Welcome to the forum, KSue. And sorry to hear of your troubles.

Yeah, there are several items not up to industry standards.

Do you have a contract with this installer? Have they been paid in full?



__________________
Tonto Goldstein... but my friends call me Bubba

Help an awesome summer camp!
Tool Guy - Kg is offline   Reply With Quote
Unread 01-01-2017, 10:50 PM   #7
Ksue28
Registered User
 
Join Date: Jan 2017
Posts: 7
No contract and Paid in Full. Because we have no idea what we are doing.

He was recommended by our original contractor bc the contractor couldn't get to it in time.

Sigh.
__________________
KSue
Ksue28 is offline   Reply With Quote
Unread 01-01-2017, 10:56 PM   #8
PetrH
Registered User
 
Join Date: Feb 2012
Location: Chilliwack, B.C.
Posts: 1,405
Waterproofing needs to go on either behind the cement board in the form of poly vapour barrier, or on top of the cement board in the form of a liquid applied waterproofing membrane. Cement board is not water proof and allows water to travel into your walls and cause mould issues. If this is a guest shower that will see limited use, then it should hold up fine, but if this is a main shower that gets used morning and night, you will have trouble with it.
__________________
Petr
PetrH is offline   Reply With Quote
Unread 01-01-2017, 10:58 PM   #9
Ksue28
Registered User
 
Join Date: Jan 2017
Posts: 7
It'll get plenty of use; it's the kids' shower and we have nine kids.

Does it help that it's a tub and tub surround? Not a free standing shower? I can't imagine having to do this all over again. I'm so frustrated right now. Wonder if we can recoup 1k and start over from this mess.
__________________
KSue
Ksue28 is offline   Reply With Quote
Unread 01-01-2017, 11:06 PM   #10
Houston Remodeler
Pondering retirement daily

STAR Senior Contributor

 
Houston Remodeler's Avatar
 
Join Date: Oct 2009
Location: Houston Texas
Posts: 28,194
Can you remove the valve handle and escutcheon plate to take a picture of the cross section of the wall like the picture below ?
Attached Images
 
__________________
Paul1

For when DIY isn't such a good idea...
Houston TX area Kitchen & Bath Remodeling


http://CabotAndRowe.com
Houston Remodeler is offline   Reply With Quote
Unread 01-02-2017, 02:09 PM   #11
rmckee84
Moderator
 
rmckee84's Avatar
 
Join Date: Feb 2012
Location: Southern Illinois
Posts: 3,006
Price seems a little low but in line with the work I see with the pics. There isn't much right with this install unfortunately. Once you contact the installer you need yo find out exactly what his methods and materials were for the installation.
What is the substrate used on the floor before tiling?
-if cement board, did he use thinset below, use appropriate fasteners, and tape his seams?
Was a moisture barrier used behind tub walls?
Were seams taped with alkali resistant tape?
The quality looks well below professional and if he didn't install things properly you may have a better chance or recouping some of your costs.
__________________
Jack of most trades, master of none...
Ryan McKee
McKee Construction & Custom Tile
rmckee84 is offline   Reply With Quote
Unread 01-03-2017, 11:03 AM   #12
Ksue28
Registered User
 
Join Date: Jan 2017
Posts: 7
We contacted the contractor and are waiting on a reply.

I know for a fact that no vapor barrier or RedGard was used because hubby and I had to supply all the materials. They just did the work for $2300.

Thank you all for your input. I'm so frustrated.

The guy also did the tub surround installation 1. Without leveling the walls so they bow and are crooked, and 2. Without covering the tub. It has fine scratches all over it and a gouge through the acrylic. It's a brand new tub. Never been used.

Did I mention he also cracked a glass block window? We've mentioned it twice and have yet to hear anything.

Needless to say, this guy is going on our black list.
__________________
KSue
Ksue28 is offline   Reply With Quote
Unread 01-03-2017, 06:33 PM   #13
Tool Guy - Kg
Moderator -- Wisconsin Kitchen & Bath Remodeler
 
Tool Guy - Kg's Avatar
 
Join Date: Feb 2005
Location: Oak Creek, WI
Posts: 21,648
Ksue,

Absent some sort of fix to your satisfaction, you might want to put small claims court in the back of your mind. I wish you the best and hopefully something can be worked out before the last resort of employing the legal system.

__________________
Tonto Goldstein... but my friends call me Bubba

Help an awesome summer camp!
Tool Guy - Kg is offline   Reply With Quote
Unread 01-03-2017, 06:40 PM   #14
cx
Moderator emeritus
 
cx's Avatar
 
Join Date: Jul 2001
Location: Boerne, Texas
Posts: 89,530
Welcome, Ksue.

Just a note for your discussions with your contractor: You do not need a vapor barrier anywhere in your tub/shower construction. You do need either an appropriate moisture barrier behind the CBU wallboard that laps over the tub's tiling flange or a direct bonded waterproofing membrane on the inside surface of your wallboard, properly attached to the tub's tiling flange unless the CBU is on the drain side of the tiling flange. But not both.

While I like and have used the Small Claims route, unfortunately you can (in my fair State) recoup only the actual cost of correcting the problem. You'll need to have someone else re-do the job before you could make any claim in Small Claims court. Better than paying lawyers, though, if you elect to have it re-done anyway.

My opinion; worth price charged.
__________________
CX

Y'ALL NEW VISITORS READ THIS HERE!
cx is online now   Reply With Quote
Unread 01-03-2017, 10:10 PM   #15
Grout-scout
Registered User
 
Join Date: Dec 2016
Location: Boerne, Texas
Posts: 14
Yikes.
__________________
Mike
Grout-scout is offline   Reply With Quote
Reply

Stonetooling.com   Tile-Assn.com   National Gypsum Permabase


Thread Tools Search this Thread
Search this Thread:

Advanced Search

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
Is this tile job acceptable? Need advice ASAP 24valemd Tile Forum/Advice Board 24 04-15-2016 09:23 AM
Tile work acceptable? Cimislia Tile Forum/Advice Board 22 11-23-2012 06:16 PM
is this an acceptable professional bathroom tile job? firefox Tile Forum/Advice Board 6 08-03-2012 12:23 AM
Acceptable subfloor under tile doug b Tile Forum/Advice Board 2 01-10-2011 07:00 PM
Acceptable tile subfloor? sdjones Tile Forum/Advice Board 10 03-08-2004 06:58 PM


All times are GMT -6. The time now is 09:06 PM.


Sponsors

Powered by vBulletin® Version 3.7.4
Copyright ©2000 - 2020, Jelsoft Enterprises Ltd.
Copyright 2018 John Bridge & Associates, LLC