Does your contract with the builder not have any language about their performing construction in compliance with applicable codes?

My building department stamps all approved job site plan sets with language to the effect that approval of the plans does not alleviate contractors of the requirement to comply with all applicable codes. I.e. if the inspector misses something or approves it, it doesn't change the contractor's duty to comply with the codes.

Cheers, Wayne
__________________
Wayne
wwhitney is offline   Reply With Quote