So I've got a bit of a problem. Pulled up some of my subfloor(all of it will eventually go) to see what the toilet plumbing is like since depending on what I can do with the toilet will determine my final bath layout.

I'm over on Terry Love getting help with moving the toilet but either way I a going to have to remove some of the waste line and sister the joist to the left of the toilet flange.

1. It is my understanding is I can sister at 2/3rds or more of the joist and not have to sister all of the way? There are some copper supplies I'd like not to have to mess with about 12 inches from one of the walls. Total span is 9ft from load bearing wall to load bearing wall.