leon,
LGB was 5 for 5 on tour first questions. As for the others:

1 I would not charge you for under cutting a couple of door jambs ( its pretty standard to do this)Install the trim before tile, I would charge if I had to make an extra trip. Tile first wood floors last. Changing this sequence for schedules sake could leave you with damaged wood floors.

2 As long as your tile man/woman knows the design of the cabinet up front it could go either way

3 If you may change the vanity later, tile the whole wall.

Larry